Eni succeeds with the first production test of Zohr field

Posted: March 11, 2016 at 11:39 am   /   by   /   comments (0)

egittoEni successfully performed the production test of Zohr 2X, first appraisal well of Zohr discovery, which is estimated in a deliverability of up to 250 MMScfd in production configuration.

Eni successfully performed the production test of Zohr 2X, first appraisal well of Zohr discovery, in the Shorouk block, offshore Egypt.

During the test, 120 m of the reservoir were opened to production. The well, constrained by surface facilities, delivered up to 44 million standard cubic feet of gas per day (MMscfd). The comprehensive set of data collected and analyzed have proved that the well has a great production capacity, which is estimated in a deliverability of up to 250 MMScfd in production configuration (about 46 thousand barrel of oil equivalent per day).

The programme envisages for 2016 the drill of further three wells. Besides, the onshore gas treatment plant construction works have already started and the bids for the offshore activities launched and nearly completed.